LEARN MISSIONpriorities, workload, recovery, collaboration, and adjustment
priorities, workload, recovery, collaboration, and adjustment
WORKED SOURCEWORKED SOURCE
Capacity plan
Weekly fixed commitments=42 h sleep, 20 classes, 12 work, and 8 meals/transport, leaving 86 h. The remaining plan allocates study 45 h, personal care 14 h, chores 8 h, errands 8 h, exercise 5 h, and social time 6 h, leaving a 0 h buffer.
A plan without buffer assumes no friction or recovery.
Trace the worked reasoning before selecting the conclusion.