Critical path

Project tasks: research 5 days, design 3 after research, build 6 after design, test 4 after build; outreach 4 can run during design/build.

  1. Sequential dependency research-design-build-test totals 18 days.
  2. Apply the method to this new case and check the strongest alternative.

What is the minimum project duration?