decomposition, algorithms, data, testing, and iteration
WORKED SOURCEWORKED SOURCETrace a scheduling algorithm
Jobs: A duration 3 deadline 4, B duration 2 deadline 8, C duration 1 deadline 3. Earliest-deadline order C,A,B completes at 1,4,6.
- Check completion against deadlines.
- Trace the worked reasoning before selecting the conclusion.
Does the order meet all deadlines?